When will the construction of the Rogun Hydroelectric Power Station be completed and how much will it cost?
The Prime Minister of Tajikistan, Kohir Rasulzoda, stated during a meeting with employees of the Rogun Hydroelectric Power Station that the country will achieve energy independence by August 2027. The President of Tajikistan, Emomali Rahmon, emphasized during his speech that the first two units of the Rogun HPP have produced 9.1 billion kilowatt-hours of electricity […]
The Prime Minister of Tajikistan, Kohir Rasulzoda, stated during a meeting with employees of the Rogun Hydroelectric Power Station that the country will achieve energy independence by August 2027.
The President of Tajikistan, Emomali Rahmon, emphasized during his speech that the first two units of the Rogun HPP have produced 9.1 billion kilowatt-hours of electricity since their commissioning, amounting to 2.1 billion somoni (approximately 219 million dollars).
Emomali Rahmon also noted that in 2026, the temporary working wheels of the fifth and sixth units are expected to be replaced with permanent working wheels, which will further increase electricity production as this step is implemented.
It is reported that the turbines and other main equipment for electricity production at the Rogun Hydroelectric Power Station are supplied by the Austrian company Voith Hydro.
The authorities have been implementing this large-scale project for many years, but almost every year the data on the final construction cost changes. Previously, the total cost was estimated at 3 billion dollars, but today this figure has increased to 8 billion dollars.
According to official data, in 2024, 2.8 billion somoni (approximately 292 million dollars) was allocated for the Rogun HPP project, but with the use of internal reserves, this amount increased to 4.8 billion somoni (over 500 million dollars). Meanwhile, in 2025, expenditures amounted to 4.3 billion somoni (about 450 million dollars).
The official and large-scale construction of this project began in 2008. However, the authorities have not yet disclosed the total expenses since the start of construction; nevertheless, the TRT GLOBAL website estimated the total investment from all sources at more than 48.1 billion somoni (about 5 billion dollars) in one of its reports.
To implement this project, Tajikistan received significant financial resources from dozens of international organizations and banks, but the total amount of loans and investments received is still not indicated in official statistics. According to official data, the World Bank has allocated a total of 650 million dollars for the project, of which 350 million dollars were provided as a grant.
In addition, the government of Tajikistan has signed financing agreements with the Asian Development Bank for 500 million dollars, with the Islamic Development Bank and Arab funds for 450 million dollars, and recently with the Qatar Development Fund for 50 million dollars. Currently, negotiations are ongoing for new loans and grants totaling 1.7 billion dollars.
It should be noted that the Rogun Hydroelectric Power Station is the largest energy project in Tajikistan, with construction completion planned for 2031. Once operational, it will become the largest hydroelectric power station in Central Asia with a capacity of 3600 MW and an annual output of 13 to 17 billion kilowatt-hours.